Facilities Project Timeline

Facility

Current Events

Parking & entrances will be changing at the DACC South Campus on State Route 23. See our latest maps.

August 10th, 2018

Completed activities include:

  •  Acoustical Wall Panel Installation in Student Dining and the Connector
  • Final Coat of Wall Paint in the Law Enforcement, Health Tech, and Admin Areas
  • Sidewalk pours on the East Side of the Building
  • Installation of VCT Flooring in the Mezzanine and Law Enforcement Area Corridors
  • Installation of Sheet Vinyl Flooring in Health Tech Areas
  • Installation of Ceiling Tile in Pharmacy Tech
  • Installation of Wood Doors in the Law Enforcement, Health Tech, and Admin Areas

Read the full executive summary.


August 3rd, 2018

Completed activities include:

  • Installation of Fire Alarm Devices
  • Installation of Flooring in the Admin Areas
  • Painting of Mezzanine Soffit
  • Installation of Lighting in the Connector
  • Installation of Ceiling Tile in the Delaware Room, Law Enforcement, Health Tech, and Admin Areas
  • MEP Overhead Rough-In in Pharmacy Tech
  • Installation of Data and Electrical Floor Boxes in the Digital Design Classrooms
  • Installation of Curtainwall in the Connector
  • Depressed Slab Pour in Area G
  • Prep for Acoustical Wall Panel Installation in Student Dining
  • Installation of Light Poles

Read the full executive summary.


July 27th, 2018

Completed activities include:

  • Installation of Ceiling Tile in Student Dining
  • Installation of Sheet Vinyl Flooring in the Main Kitchen
  • Installation of FRP in the Professional Food Service Kitchen
  • Delivery of Kitchen Equipment
  • Installation of Ceiling Grid in the Law Enforcement and Health Tech Areas
  • Installation of Lighting and HVAC Grilles in Law Enforcement and Health Tech Areas
  • Installation of Lighting and HVAC Grilles in the Admin Areas
  • Painting of Exposed Overhead Structure in the Connector
  • Installation of Ceiling Grid in Admin Areas
  • Installation of Fire Stopping in the Mezzanine Corridor

Read the full executive summary.


July 20th, 2018

Completed activities include:

  • Above Ceiling Structural and Fire Suppression System Inspections in Areas D and E
  • Installation of ‘DACC’ and ‘RAMTEC’ Exterior Signs
  • Paint Prep in the Law Enforcement and Health Tech Areas
  • Painting of the Exposed Ceiling in the Connector
  • Installation of Ceiling Tile in the High Bay Lab Corridors
  • Prep for Sheet Vinyl Flooring in the Main and Professional Food Service Kitchens
  • Installation of Perforated Metal Panels in Stair Handrails and Mezzanine Guard Rails
  • Installation of Ceiling Grid in Admin Areas
  • Painting of Drywall on the Mezzanine

Read the full executive summary.


July 13th, 2018

Completed activities include:

  • Installation of Security Cameras in High Bay Area Corridors
  • Polished Concrete Application in Areas D, E, and Student Dining
  • Sawcutting of Concrete Floors in Existing Building
  • Spray Fireproofing Application of Renovation Areas to be Turned Over at the End of the Summer
  • Painting of High Wall in the Connector
  • Finishing of Drywall in the Admin Areas

Read the full executive summary.


July 6th, 2018

Completed activities include:

  • Erection of Structural Steel for the New Portion of the High Roof in Area G
  • Delivery of Toilet Compartments and Dressing Partitions
  • Delivery of Wood Doors
  • Installation of Ceiling Grid in the Law Enforcement Multi Purpose Room
  • Installation of Branch Gas Line to RTU’s and Generator
  • Painting of Metal Pan Stair Handrails in the Connector

Read the full executive summary.


June 22nd, 2018

Completed activities include:

  • Installation of Ceiling Grid in the Main Kitchen
  • Installation of Vinyl Tile Flooring and Rubber Wall Base in the New Server Room
  • Relocation of Spectrum Fiber and Power Cut Off to Existing Building
  • Polished Concrete Application in the North-South High Bay Lab Corridor
  • Installation of Rubber Wall Base in High Bay Lab Areas
  • Installation of Casework in High Bay Lab Areas
  • Hydrostatic Testing of Sprinkler System in High Bay Lab Areas
  • Fit out of Technology Closet TR4
  • Re-roofing of the Existing Building

Read the full executive summary.


June 15th, 2018

Completed activities include:

  • Installation of Spandrel Glass in the Connector
  • Installation of Mezzanine Guardrails
  • Installation of Ceiling Tile in Restrooms, Offices, and Shared Classrooms in the East-West High Bay Lab Corridor
  • Setting of Energy Distribution Systems in Kitchens
  • Selective Demolition in the Health Tech Area
  • Delivery of Casework
  • Installation of Elevator Shaft Lining
  • Asbestos Abatement in the Existing Building

Read the full executive summary.


June 8th, 2018

Completed activities include:

  • Above-Ceiling Electrical Inspections for High Bay Labs in the East-West Corridor
  • Above-Ceiling Plumbing and HVAC Inspections for all High Bay Areas
  • Sidewalk pour at Southwest Entrance of the Building
  • Installation of Lighting and Fire Alarm Devices in the North-South High Bay Lab Corridor
  • Stair Riser pour in Connector Metal Stairs
  • Installation of Hand Rails on North Stairs in the Connector
  • Delivery of Energy Distribution System
  • Fireproofing of Law Enforcement Area
  • Installation of Elevator Car

Read the full executive summary.


May 25th, 2018

Completed activities include:

  • Painting of Bollards in Courtyard
  • Slab on Grade pour at West Entry into Connector
  • Delivery of Acoustical Ceiling Tile
  • Delivery of Terra Cotta Wall Panels
  • Installation of Elevator Sump Pump
  • Installation of Pathways for Technology to Main Tech Closet

Read the full executive summary.


May 18th, 2018

Completed activities include:

  • Level 5 Finish in High Bay Corridors
  • RTU Startup
  • Installation of Lockers in High Bay Labs
  • Sidewalk pour along East side of the building
  • Installation of Wire Mesh Partitions in High Bay Labs
  • Roofing over Connector Area
  • Installation of Metal Fascia and Soffit complete around the High Bay Labs
  • Installation of Plumbing and Light Fixtures in High Bay Labs

Read the full executive summary.


May 11th, 2018

Completed activities include:

  • Permanent Power to the Building
  • Finish Coat and Striping of Asphalt Paving in Courtyard
  • Placement of Concrete Curbs in Courtyard
  • Metal Panel Installation in Connector Courtyard
  • Slab on Grade pour in Connector
  • Installation of Blocking in the Admin Area
  • Installation of Ductwork at Professional Food Service, Culinary Arts, Main Kitchen Areas, and Second Floor

Read the full executive summary.


May 4th, 2018

Completed activities include:

  • Base and Intermediate Coat of Asphalt Paving in Courtyard
  • Elevator Pit Prep for Elevator Install
  • Installation of Elevator Shaft Walls
  • Drywall Finishing on the Second Floor
  • Installation of Walk Mats on the Roof
  • Installation of Main Gas Line on the Roof

Read the full executive summary.


April 27th, 2018

Completed activities include:

  • Installation of Paint Booth (Initial Phase)
  • Stone base for Asphalt Paving
  • Initial Grind of Polished Concrete in South and North Corridor of High Bay Areas
  • Installation of Translucent Sandwich Panels
  • Installation of Exterior Masonry Veneer in Early Childhood Development Area
  • Slab on Grade pour in Early Childhood Development Area
  • Delivery of Elevator

Read the full executive summary.


April 13th, 2018

Completed activities include:

  • Exterior Framing and Sheathing at the Connector
  • Installation of Metal Framing in Admin Area
  • Installation of Walk-in Coolers in the Main Kitchen and Culinary Arts Kitchen
  • Installation of metal decking at the Connector

Read the full executive summary.


April 6th, 2018

Completed activities include:

  • Ceramic Tile in Restrooms of High Bay Labs
  • Installation of Two Roof Hatches
  • Structural Framing from Existing Building to Connector
  • Electrical and Plumbing In-Wall Rough-In in Area E
  • Installation of Drywall on Second Floor

Read the full executive summary.


March 30th, 2018

Completed activities include:

  • Partial Slab on Grade pour in Connector
  • Installation of Exterior Overhead Coiling Doors in High Bay Labs and Paint Booth
  • Installation of Bollards in Courtyard
  • Exterior Framing and Sheathing of Early Childhood Development Area
  • Metal Framing at Culinary Arts, Professional Food Service, and Main Kitchen Areas
  • Installation of Ceiling Grid in Classrooms
  • Installation of Switchgear

Read the full executive summary.


March 23rd, 2018

Completed activities include:

  • All Drywall has been Installed on Areas A, B, and C
  • Setting of Rooftop Air Handling Units
  • Installation of Interior Masonry Veneer in South Corridor of Connector
  • Preparation for Slab on Deck pour of the Stairs on the Second Floor
  • Preparation for Slab on Grade pour in Connector
  • Installation of Roof Curbs and Flashing for Kitchen Equipment
  • Installation of In-Wall MEP at Digital Design and Networking Area

Read the full executive summary.


March 16th, 2018

Completed activities include:

  • Slab on Grade pour in new Admin Area
  • Slab on Grade pour for Freezers/Coolers
  • Preparation of Subgrade Stone for Slab on Grade pour in Connector
  • Dynamic Glazing Installation on North and West Elevations

Read the full executive summary.


March 9th, 2018

Completed activities include:

  • Installation of Interior Masonry Veneer at the Corridor 1009
  • Dynamic Glazing Installation on South Elevation
  • Preparation for Slab on Grade pour on new Admin Area
  • Installation of Fans in Construction and Power Lines
  • Overhead Coiling Door Installation in Power Lines and Construction Tech
  • Installation of Metal Panels on West Elevation of the new building
  • Installation of Roofing at Admin Area

Read the full executive summary.


March 2nd, 2018

Completed activities include:

  • Installation of Roof Vapor Barrier of Early Childhood Development and Admin Areas
  • Structural Steel Detailing at Connector
  • Painting in Power Line and Construction Tech Labs
  • Installation of Curtain Wall Framing and Dynamic Glass Wiring at South and West Elevations
  • Preparation and slab pour for Admin Area

Read the full executive summary.


February 23rd, 2018

Completed activities include:

  • Installation of Interior Framing at Digital Design Area
  • 1st coat painting in Power Line and Construction Tech Labs
  • Installation of Underground MEP at Admin Area
  • Steel Decking at Building Connector

Read the full executive summary.


February 16th, 2018

Completed activities include:

  • Installation of drywall in Construction Tech and Power Line offices
  • Installation of electrical rough-in in Auto Tech lab
  • Installation of ductwork in Auto Tech lab
  • Installation of exterior framing and sheathing in administrative area
  • Fireproofing of the kitchens and student dining area
  • Foundation block for connector

Read the full executive summary.


February 12th, 2018

View the drone footage flyover to see how much the campus has grown.

 


February 9th, 2018

Completed activities include:

  • Installation of plumbing rough-in in the Auto Tech lab
  • Installation of window and door frames in the Auto Tech lab
  • Installation of MEP in-wall rough-in at Digital Design area

Read the full executive summary.


February 2nd, 2018

Building principals from all of our partner districts took time out of their day to tour the addition and talk about how our students will benefit from being under one campus.

 

Interesting fact of the week:

  • 4,750 linear feet of ductwork has been installed

Completed activities include:

  • Framing of clerestory walls in the Auto Technology lab
  • Placement of concrete foundations and piers in the "A"
  • Installation of hydronic piping in Engineering Technology and Auto Technology labs
  • Installation of MEP hangers in Student Dining and Culinary Arts lab
  • Installation of Roof Decking in Fire Servicing Technology lab
  • Fireproofing in Digital Design area

Read the full executive summary.


January 30th, 2018

What was once an open wide open space is now a series of labs and classrooms. Hear from Elford Incorporated Project Manager, Ted Kelleher, about the progress of the construction project and how they are working through the freezing temperatures.


January 26th, 2018

Interesting facts to date:

  • 3,300 cubic yards of concrete have been poured
  • 105,000 square feet of drywall have been placed
  • 5,260 metal framing studs have been installed

Completed activities include:

  • Installation of masonry veneer at the courtyard
  • Installation of plumbing rough-in in Engeering Technology lab
  • Installation of drywall & insulation of south corridor
  • Pour slab on grade in Culinary Arts lab
  • Erection of structural steel in Administration area, Early Childhood lab, and Fire Service Training lab
  • Installation of decking in Administration area and Early Childhood Education lab 

Read the full executive summary.


January 19th, 2018

Completed activities include:

  • Framing of clerestory in area B
  • Slab on grade pour in area D
  • Erection of structural steel in area F
  • Hydronic piping in area A
  • Installation electrnical rough-in in areas A & B

Read the full executive summary.


January 12th, 2018

Completed activities include:

  • Installation of plumbing rough-in in area A
  • Installations of Window blocking in southwest elevations
  • Installation window & door frames in area, A & B
  • Framing of Clerestory in area A
  • Installation of sprinkler system in areas A & B
  • Slab on grade prep in areas D & E
  • Pour slab on grade section in area D
  • Installation of masonry veneer on south elevation

Read the full executive summary.


January 5th, 2018

Completed activities include:

  • Installation of ductwork in area B
  • Installation of underground electric in areas D & E
  • Removal of west elevation exterior panels
  • Demolition of existing building

Read the full executive summary.


December 21st, 2017

Completed activities include:

  • Rough-in of in-wall electric in area A
  • Temporary wall in the Telecommunication Room
  • Relocation of security and RTU controls in existing building

Read the full executive summary.


December 18th, 2017

DACC Director of Operations, talks about when the addition will be connected to the existing south campus and how Elford is working with us to accommodate our testing schedules.

 


December 15th, 2017

DACC celebrated the remobilization of construction with a Beam Signing Ceremony for all who were closely involved in getting construction back on track. The ceremony was held exactly one year after receiving news of the invalidated levy.


December 8th, 2017

Central Office staff are  now housed at the North Campus until their final office spaces in the renovated south campus are complete. The previous Central Office spaces at the south campus are now under construction. Demolition of the south wall is being prepared in order to connect the addition to the existing south campus building.

Completed activities include:

  • Exterior insulation in south, east, west, and courtyard area
  • Underground plumbing in area D and E
  • HVAC hangers in area A and B
  • Underground electric in area D

 

Read the full executive summary.


December 4th, 2017

Students at the north and south campuses were invited to sign beams that will be placed in the main entrance of the newly renovated/constructed building to forever put their mark on the Delaware Area Career Center.

 

Watch the video invitation issued by DACC Superintendent, Mary Beth Freeman:


December 1st, 2017

Completed activities include:

  • Mezzanine slab on deck in Area D & E

Read the full executive summary. 


November 30th, 2017

As the construction/consolidation project remobilizes, DACC's Superintendent, Mary Beth Freeman, shares what this means for the project,  project, the timeline, and for our students.

 


July 21st, 2017

Complete activities include:

  • Patching and milling the asphalt on Peachblow Road
  • Spreading remaining top soil for final grading and backfilling curbs
  • Placement of concrete curbs around parking lots
  • Placement of concrete approaches at new driveways

Read the full executive summary.


July 14th, 2017

Complete activities include:

  • Cast in place concrete for the paint booth pit in Area C
  • Placement of interior concrete slabs on grade in Area C
  • Placement of concrete for new sidewalk in East Parking Lot

Read the full executive summary.


July 7th, 2017

Complete activities include:

  • Placement of concrete slab for polished concrete in Area B
  • Placement of interior concrete slabs on grade in Area B

Read the full executive summary.


June 15th, 2017

The DACC Board of Education toured the addition and walked through future lab spaces, classrooms, and the cafeteria.

 

 


June 2nd, 2017

Complete activities include:

  • Installation of rooftop equipment support framing
  • Installation of oil and grease interceptors in the courtyard
  • Placement of concrete curbs in the South parking lot
  • Sitework and underground electric for the Glenn Parkway turn lane

Read the full executive summary.


May 19th, 2017

Complete activities include:

  • Installation of the primary & secondary electric service line in the courtyard
  • Installation of gravel base for parking lots
  • Roofing Areas A through C
  • Installation of temporary enclosures in Areas A and B

Read the full executive summary.


May 5th, 2017
Complete activities include:

  • Construction of masonry firewall
  • Installation of underground plumbing in Area C
  • Metal stud framing Area D
  • Sheathing the exterior of Area D

   

Read the full executive summary.


April 28th, 2017
Complete activities include:

  • Installation of underground plumbing in Area B
  • Installation of underground electric in Area A
  • Reconstruction of the existing LGIA
  • Placement of concrete footings in Area J and at temporary enclosure wall
  • Installation of light pole bases in the South Parking Lot

   

Read the full executive summary.


April 21st, 2017
Complete activities include:

  • Installation of structural steel in Area E to column line 21
  • Metal stud framing Area C
  • Sheathing the exterior of Areas A, B, and C
  • Installation of underground plumbing in Areas A and B
  • New gas line to future Burn Building

   

 

Read the full executive summary.


April 14th, 2017
Complete activities include:

  • Metal stud framing in Area B
  • Installation of storm structures in the courtyard

​Read the full executive summary.


April 7th, 2017
Complete activities include:

  • Metal stud framing in Area A
  • Installation of metal decking in Area D

Read the full executive summary.


March 31st, 2017
Complete activities include:

  • Grouting masonry foundations in Areas C, D, and F
  • Installation of structural steel in Area D to column line 21
  • Backfilling of masonry foundations in Area H
  • Installation of masonry firewall to scaffold height

   

Read the full executive summary.


March 24th, 2017
Complete activities include:

  • Receipt of conditional building permit for Liberty Township
  • Tie-in of water line to existing fire protection system
  • Installation of the water line backflow preventer and water meter vault
  • Flushing and testing of the remaining water line system
  • Installation of masonry foundation in Area H
  • Backfilling of masonry foundations in Areas C, D, and F

   

 

 

Read the full executive summary.


March 10th, 2017
Complete activities include:

  • Installation of perimeter masonry foundations in Area D
  • GMP No. 3 Contractor Kick-Off meeting

   

Read the full executive summary.


March 3rd, 2017
Complete activities include:

  • Installation of remaining masonry foundation in Area C
  • Placement of concrete foundations in Areas F & H
  • Placement of concrete foundation for the firewall
  • Flushing and testing of available portion of the new water line system
  • Installation of perimeter masonry foundation in Area D

   

Read the full executive summary.


February 24th, 2017
Complete activities include:

  • Finished the remaining concrete perimeter foundations in Areas C & D.
  • Installation of structural steel for Areas A, B, & C
  • Finished the building pad for Areas C & D
  • Gas line connection to temporary meter from Columbia Gas
  • Relocation of existing technology & utility pathways
  • Installation of water lines

Read the full executive summary.


February 17th, 2017
Complete activities include:

  • Approval of GMP No. 3 by the Board of Education
  • Installation of structural steel columns, beams, and joists in Areas A & B
  • Completion of the elevator pit

Read the full executive summary.


February 10th, 2017
Complete activities include:

  • Placement of perimeter and interior concrete foundations in Area E
  • Grouting CMU foundations in Area B
  • Crane delivery and start of structural steel erection

 

Read the full executive summary.


February 3rd, 2017
Complete activities include:

  • Storm structures to the north east retention pond
  • Storm structures along the new driveway
  • Delivery and assembly of the steel-erection crane

Read the full executive summary.


January 20th, 2016
Complete activities include:

  • Received bids for Design Release No. 3
  • Installation of fire hydrants
  • Installation of CMU foundation in Areas A and B
  • Completion of building pad for Area E
  • Addition of a new construction access road

Read the full executive summary.


December 30th, 2016
Complete activities include:

  • Installation of sanitary lines in existing parking lot
  • Installing of secondary feeders to new switchgear
  • Pulling of low voltage wiring in existing building
  • Installation of new switchgear and domestic water line tie-in

Read the full executive summary.


December 23rd, 2016
Complete activities include:

  • Installation of storm sewers along the north portion of the site
  • Relocation of fiber optic service and power for cell tower
  • Installation of transformer
  • Removal of tanks along the north end of the existing building
  • Design Release No. 3 (Building) received on 12/22/16

Read the full executive summary.


December 9th, 2016
Complete activities include:

  • Trenching for gas line installation
  • Relocation of fiber optic service for the building
  • Delivery of new switchgear
  • Installation of water line to the burn building area

Read the full executive summary.


December 2nd, 2016
Complete activities include:

  • Underground electrical raceways for lights in parking lot
  • Relocation of underground power line
  • Asphalt paving for new access road
  • Installation of temporary signage for traffic control
  • Site rough grading along the east portion of the site

 

Read the full executive summary.


November 18th, 2016
Complete activities include:

  • Finalizing GMP No. 2
  • Installation of new fiber optic service lines along St. Rt. 23
  • Grading along the north and west ends of the existing building for road replacement
  • Installation of conduits for new electrical service along the north end

Read the full executive summary. 


November 4th, 2016
Safety fencing has been put in place, temporary power line poles have been installed, and machines are grading the area for the addition.

     


October 14th, 2016
Completed activities include:

  • Installation of power poles for temporary power
  • Installation of temporary facilities for Elford
  • Installation of erosion and sediment control measures along the perimeter of the site

Read the full executive summary.


September 28th, 2016
DACC held the official Groundbreaking Ceremony to kick off construction work for the renovation/addition. Representing DACC, SHP Leading Design, and Elford Inc. on the shovels are:

  • Ted Backus, DACC Board Member
  • Jim Hildreth, DACC Board Member
  • Ed Bischoff, DACC Board Member
  • Tom Kaelber, DACC Board Vice-President
  • Julie Wagner-Feasel, DACC Board President
  • Mary Beth Freeman, DACC Superintendent
  • Chris Bell, DACC Treasurer
  • Jack Higgins, DACC Director of Operations
  • Gregg Gaber, SHP Leading Design Managing Principal
  • Carrie Malatesta, SHP Leading Design Senior Interior Designer
  • Eric Bull, Elford Inc., Executive Vice President
  • Jim Smith, Elford Inc., CEO

Sheriff Russ Martin addressed the attendees along with DACC Board President, Julie Wagner-Feasel and DACC Superintendent, Mary Beth Freeman. DACC Food Service and Culinary Arts students provided refreshments. DACC Law Enforcement students greeted guests and escorted them through the rain.

       


August 18th, 2016
SHP Leading Design presented the DACC Board of Education with a virtual walk-through of the newly renovated building. All furniture and interior decorations are placeholders only.

 


July 21st, 2016
Representatives from SHP Leading Design and Elford Construction presented updates on the building project to the DACC Board of Education. At this point in time, the design phase is 70% complete. Timelines have been established as to when specific areas of south campus will be renovated. This timeline has been scheduled around instruction with minimal disruption to students. Select south office staff will temporarily move to the north campus while the south campus is being renovated.

SHP presented updated renderings of the site plan and interior and exterior preliminary designs. The updated site plan adds a detention pond in the South East corner to allow more space for the fire training grounds in the North East corner. The plan includes a great deal of natural and diffused light into the building while the interior focuses on flexible space for future use.

Elford is working on cost estimating and taking opportunities to shrink the schedule where possible. One such example is purchasing prefabricated electrical to save time on installation.

 


April 25th - 28th, 2016
SHP Leading Design met with lab and academic instructors to review classroom settings in more detail. Instructors provided input about where furniture and equipment will be placed, how students will flow in and out of their classrooms, where locker and storage spaces will be, and addressing any and all safety needs. Feedback from DACC staff and instructors has been a valuable part of the design process.


April 21st, 2016
Following an extensive stakeholder and community engagement process,the Delaware Area Career Center Board of Education approved the schematic design. In total, the facility features 118,816 square feet of hands-on learning labs with an additional 105,958 square feet of academic core spaces.

Members of each program, including staff and administrators, as well as community and business leaders, have been actively involved in the design process to create customized spaces suited to the needs of the program and the industry as a whole.

A number of site access and safety enhancements will be made to accommodate increased traffic flow on the site. The direct access path to US Route 23 on the west side of the building will be removed and a new Glenn Parkway access road will be created on the east side of the existing parking lot. This new Glenn Parkway entrance will serve as the primary entrance and exit route for buses and adult students. The existing parking lot access road south of DACC on Glenn Parkway will remain and serve as the primary entrance for students and faculty. Pedestrian traffic will be altered as well with separate entrances for high school students and adult students.

Aerial Rendering

Aerial Rendering

Artist's Rendering - Front Entrance

Artist's Rendering - Side Entrance


April 13th, 2016
SHP Leading Design presented further updates of the schematic design to the DACC Board of Education. The BOE will be voting on the final schematic design at the upcoming April 21st board meeting before entering into the Design Development stage.

Elford Inc also presented updated estimated costs to the BOE and expressed confidence that the project is projected to remain in budget. At this point, there are many opportunities to make cost-cutting decisions.

 


March 9th, 2016
SHP Leading Design presented updated drawings to the DACC Board of Education that included the overall site plan, new entrances that have been reviewed with city agencies and emergency services, and inspiration for the beginnings of interior and exterior designs. The new site plan removes the drive that exits directly onto State Route 23 and adds a driveway along the back of the building. These changes were in response to DACC BOE comments at the February work session.

 


March 8th, 2016
SHP Leading Design continued to meet with DACC staff, including non-instructional staff such as Maintenance, IT, Student Services, the Cafeteria, and the Media Center. Throughout this process, every department has provided input regarding the future of their space. 

 

 


February 23rd, 2016
DACC Superintendent, Mary Beth Freeman, held an all staff meeting to present the preliminary building design that the DACC Board of Education saw on February 10th.

 


February 15th, 2016
Members of the DACC Administrative Team met to review changes made since the board meeting. Preliminary designs for the interior and exterior were also presented.

 


February 10th, 2016
SHP Leading Design presented a preliminary site plan to the DACC Board of Education. This was the first time the BOE had seen preliminary designs. The BOE had time to voice comments, questions, and concerns. The next opportunity for the BOE to see updated drawings will be March 9th at the March work session.

 


February 3rd, 2016
The DACC Administrative Team reviewed changes to the preliminary building layout.

 


January 26th & 29th, 2016
Lab and academic teachers reviewed building plans for the first time to discuss overall locations of class spaces. SHP Leading Design also interviewed teaching staff about the way curriculum is delivered and the wants and needs they have for their programs.

 


January 22nd, 2016
Members of the DACC Administrative Team discussed the preliminary building layout. Topics at this meeting focused on parking lots, bus routes, and keeping student and community entrances separate to increase safety.

 


January 21st, 2016
The DACC Board of Education voted to approve the construction document with SHP Leading Design. This document included the budget amount of $45 million.


December 9th, 2015
SHP Leading Design gave a presentation to the DACC Board of Education at a special meeting.


November 19th, 2015
The DACC Board of Education approved the contract with Elford Construction.


November 11th, 2015
SHP Leading Design gave a presentation to the DACC Board of Education at a work session.


August 31st, 2015
DACC Administration held a second Facebook Q&A to discuss the facilities project.


August 27th, 2015
The DACC Board of Education selected Elford Construction as the Construction Manager at Risk at the August board meeting.


August 25th, 2015
DACC Administration held a community form at the north campus to discuss the facilities project.


August 13th, 2015
DACC Administration held a Facebook Q&A to discuss the facilities project.


August 4th, 2015
DACC Administration held a community forum at the south campus to discuss the facilities project.


August 3rd, 2015
The DACC Board of Education held interviews for the Construction Manager at Risk at a special meeting.


May 21st, 2015
The DACC Board of Education selected SHP Leading Design to provide design services for the facilities project.


April 29th, 2015
The DACC Board of Education interviewed potential architects at a special meeting.


March 10th, 2015
The DACC Board of Education authorized the Construction Manager at Risk process for the Consolidation of Facilities Project at a special meeting.


December 18th, 2014
The DACC Board of Education voted to consolidate the high school and adult education programs at the south campus location. This decision was based on a year-long study that included meetings with focus groups, facility studies, and input from associate districts. Benefits to moving to the south campus include:

  • The location is visible and easily accessible to the   community, an attribute that external focus groups determined was essential.
  • The land provides more options for expansion.
  • For each district, travelling to south campus either   cut down on travel time or made little-to-no negative impact on travel time compared to travelling to north campus.
  • South campus is near the center of Delaware County.

December 10th, 2014
At the December work session, the DACC Board of Education reviewed the site analysis and discussed topics such as development space, parking capacity, building height restrictions, and set back restrictions. The Board of Education also discussed the site options and the pros and cons of each option. At this stage, the options were to renovate/build at the north campus, renovate/build at the south campus, or start at a new piece of land.


November 12th, 2014
The DACC Board of Education reviewed the facilities report and a site analysis at a work session. Topics discussed included site development, programming, logistics, and information that came from the focus groups.


October 8th, 2014
Quandel Enterprises presented a Facilities Assessment to the DACC Board of Education at a work session. They discussed factors to consider, overall planning, and possible funding.


June 2014
Internal and external focus groups were held to discuss what education looks like today and what it will look like in the future. These groups provided valuable insight that led to many of the decisions that would be made in the future.


Fall 2013
DACC requested that a feasibility study be conducted on the existing space at both campuses. This feasibility study kicked off the discussion of whether or not the DACC Board of Education could pursue combining campuses and lasted approximately one year.